In the case where an assessee has claimed any deduction out of the initial cost of the development of infrastructure facility of roads/highways under BOT projects in the earlier year, the total deduction so claimed for the Assessment Years prior to the Assessment Year under consideration be deducted from the initial cost of infrastructure facility of roads/highways and the cost ‘so reduced’ be amortised equally over the remaining period of toll concessionaire agreement.Trade Circular VAT liability of developers – computation – Trade Circular 12T of 2014 dated 17-04-2014.
This Circular is applicable only to those infrastructure projects for development of road/highways on BOT basis where ownership is not vested with the assessee under the concessionaire agreement.