Part B — Unreported Decisions
(Full texts of the following Tribunal decisions are available at the Society’s office on written request. For members desiring that the Society mails a copy to them, Rs.30 per decision will be charged for photocopying and postage.)
1 ITO, 14(3)(3) v.
Shri Vimalchand M. Dhoka
ITAT ‘A’ Bench, Mumbai
Before K. C. Singhal (JM) and V. K. Gupta (AM)
ITA No. 5520/Mum./2005
A.Y. : 2002-03. Decided on : 19-5-2008
Counsel for revenue/assessee : Sanjay Agarwal/
Vimal Punmiya
S. 80IB(10) of the Income-tax Act, 1961 — In respect of Lonavala Project of the assessee for which deduction was claimed u/s.80IB(10), land was purchased in 1996 — Wall was constructed — WIP of this project on 31-3-1998 was stated to be Rs.10,17,615 — Original plan expired after validity period of one year — Revised plan was approved and commencement certificate issued on 30-9-2000 — User of land for non-agricultural purposes was permitted on 28-6-2001 — Whether AO justified in denying deduction u/s.80IB(10) on the ground that the condition u/s.80IB(10)(a) viz. commencement of the construction after 1-10-1998 was not satisfied — Held, No.
Per V. K. Gupta :
Facts :
The assessee was engaged in the business of textiles and construction. In A.Y. 2002-03, in respect of construction business, the assessee claimed deduction u/s.80IB(10) at Rs.62,21,131 in respect of his projects at Virar and Lonavala. In respect of Lonavala project, land was purchased in 1996 for Rs.5.50 lakhs and work-in-progress as on 31-3-1998 was shown at Rs.10,17,615. The AO disallowed the claim for deduction u/s.80IB(10) of Rs.3,32,369 in respect of Lonavala project, on the ground that the project had commenced prior to 1st October 1998, since land for Lonavala project was purchased in 1996 and as on 31st March 1998, certain expenses were shown as work-in-progress and also a wall was constructed. According to the AO, the project did not satisfy the condition stated in S. 80IB(10)(a). Before the CIT(A) the assessee contended that :
(a) no construction work actually took place before 1st October 1998;
(b) the wall was constructed merely to prevent the entry of trespassers;
(c) the plan, originally submitted, expired after the validity period of one year, hence revised plan was submitted, which was approved by the concerned statutory authorities and, thereafter construction work started after 1-10-1998;
(d) the land was an agricultural land and conversion of land use was permitted only on 28-6-2001;
(e) the expenses shown in the balance sheet were of administrative nature and not of construction activity. The CIT(A) found force in the arguments of the assessee that the expenses incurred on architect fees, landscape and elevation on filling the plot are the expenses which were necessary for submitting the plan for the project and that incurring of these expenses cannot be taken as commencement of the project. The fact that permission for conversion of land from agricultural use to non-agricultural use was issued on 28-6-2001 and also the commencement certificates were issued by the relevant authority only on 30-9-2000 also weighed with the CIT(A). The CIT(A) also stated that before getting the order for conversion and commencement certificate, the construction activity cannot be started. He, therefore, agreed with the assessee and directed the AO to grant deduction to the assessee as claimed by it. The Revenue preferred an appeal to the Tribunal.
Held :
The expenses incurred for change of land use and other administrative/other land development expenses incurred prior to statutory approvals, which approvals have been received after 1st October 1998 cannot result into commencement of the project before 1st October 1998. The Tribunal observed that the CIT(A) has examined the issue in detail and found itself to be in agreement with the findings of the learned CIT(A), hence the Tribunal confirmed the order passed by CIT(A). Accordingly, appeal filed by the Revenue was dismissed.