The assessee, a real estate developer obtained approval for a housing project on 16-03-2005 from the Development Authority. It completed the project in 2008 and by a letter dated 05-11-2008 applied to the Competent Authority for the issue of the completion certificate. The assessee’s claim for deduction u/s. 80-IB(10) was denied inter alia, on the ground that the completion certificate was not obtained within the period of four years as prescribed by the Finance Act, 2004 w.e.f. 01-04-2005. The Tribunal allowed the assessee’s claim for deduction accepting the assessee’s claim that, since the approval was granted to the assessee 16-03-2005 i.e., prior to 01-04-2005, the assessee was not expected to fulfill the conditions which were not on the statute when such approval was granted to the assessee.
On appeal by the Revenue, the Delhi High Court upheld the decision of the Tribunal and held as under:
“i) The approval for the project was given by the Development Authority on 16-03-2005. Clearly, the approval related to the period prior to the amendment, which insisted on the issuance of the completion certificate by the end of the four year period, was brought into force. The application of such stringent conditions, which are left to an independent body such as the local authority who is to issue the completion certificate, would have led to not only hardship but absurdity.
ii) As a consequence, the Tribunal was not, therefore, in error of law while holding in favour of the assessee.”