Facts:
The appellant provided ‘Construction service’/ ‘Commercial or industrial construction service’ and availed benefit under Notification No. 15/2004-ST and Notification No. 1/2006-ST for respective period of time. The Revenue contested that appellant provided completing and finishing services and hence abatement under Notification 1/2006-ST could not be availed. Also, it was argued that in order to avail such abatement, the gross value of revenue should include Free of Cost (FOC) materials before availing abatement of 67%.
Held:
It was held that the appellant was eligible to claim exemption under the said Notification and a complete waiver of the demand before the appeal was allowed and a stay order was sustained on collection of all demands arising out of the order during the pendency of the appeal.